Technical Study: Level Threshold Detailing

Level thresholds can be very difficult to detail, with many standard details always showing a 150mm step between the finished floor level and external ground level. However, level thresholds provide a future proof solution to an aging population, and make sure a building can be used and visited by everyone. They are also a very aesthetic solution to bridging the gap between indoors and outdoors.  

Level thresholds are a legal requirement for new build housing in the UK. This means that all external doors, front, rear and side, plus any sliding, bifold, French or terrace doors need to provide a level entrance and exit. Although it is not a building regulation requirement in renovation projects, some councils may require level thresholds as a planning condition within extensive renovation projects.  

Below we look at key considerations when designing level thresholds to make sure water does not enter the building.

[To Download a FREE PDF of this guide scroll to the end]

Level threshold detail
Level Threshold: A threshold that is level or, if raised, has a total height of not more than 15mm, a minimum number of upstands and slopes and with any upstands higher than 5mm chamfered.

Accessible / Level Threshold

An accessible threshold is defined as a threshold this is level or, if raised, has a total height of not more than 15mm, a minimum number of upstands and slopes and with any upstands higher than 5mm chamfered.  

Building Regulation Requirements

 

 

For single new build properties, Building Regulation Part M4(1) and M4(2) must be met. This requires all access to the dwelling to be step free, including the entrance, garden and any terraces. For larger developments or flats, the local council may require 10% of units to meet Building Regulations Part M4(3), meaning the unit is fully adaptable to a wheelchair user.

Whilst these Building Regulations do not need to be met in the case of an extension, some Local Authorities, Building Control and/or Approved Inspectors may require the need to meet Part M4(1) within a planning approval condition, requiring entrances and exits to the house to be accessible.

 

Ground Floor Level Thresholds

Level threshold
[Left] In-situ concrete threshold drain built under the sill and pavers, pavers to be removable or inspection hatch to be provided at either end of the drain for cleaning and maintenance.  
[Right] Aluminium threshold drain installed between pavers and sill with removable grill for inspection, drain with low level water entry of water infiltration between drain and sill.  
Flush Threshold with Concrete Sill

There are various ways of designing a level threshold based on aesthetic, cost, structure, site conditions and location. However, there are a number of key features that all level thresholds should take into account.

Door – When specifying a door to be used in a level threshold, most manufacturers will state if the system is compliant with Part M of the Building Regulations. This guarantees that the element you step over is no more than a maximum 15mm in height with no upstands of more than 5mm. Most sliding door manufactures provide frames with a completely level base frame. However, it is important to check the base frame of elements such as front and rear doors, especially in timber, as these will need special aluminium thresholds to be fully accessible.

Threshold Drainage – This is a building regulations requirement when designing this type of threshold. A drain can be installed between the sill and external landscaping flush with the level floor or hidden under the finishes.

Many door manufacturers will even be able to provide a threshold drain for the door system chosen. This will help drain away any water near the drain as well as water which hits the door or glass and drains through the frame. ​

level threshold sliding doors

[Above] Threshold drain designed to clip into the aluminium sliding door system to drain both surface rain and rain hitting the glass and filtering through the window frame.

Waterproofing – Damp proof membranes should be draped up the door or window frame system at the point of the threshold. Water should be moved away from the threshold, by sloping eternal finishes away from the drain. To either side of the threshold, the damp proof course should be minimum of 150mm above ground level.

Key points to remember

 

  • The threshold including door frame should not be more than 15mm in height overall. Of these 15mm, there should be a minimum number of upstands and slopes, with any upstands higher than 5mm chamfered.
  • If the threshold is exposed to wind driven rain the landing can be up to 10mm below the level of the sill if the sill is rounded or chamfered.
  • The external landing should have a fall ratio of between 1:40 and 1:60.
  • Ensure all water falls away from the doorway in a single direction.
  • Build a drainage channel between the landing and the threshold.
  • Ensure the channel discharges to a drainage system or land drainage such as a soakaway.

Timber Frame Key Considerations

Timber Wall Raise Foundation
[Left] Timber frame construction either side of threshold showing concrete slab construction and raised foundation blocks 150mm above finished floor level, with threshold drain.  
[Right] Level threshold with drain  
07 Timber Wall Level Threshold
Usually when designing for a timber frame structure, the timber frame should begin 150mm above the ground level. This concept should be maintained when the ground level externally is level with the internal finish floor level. All the same considerations as above should be taken to account as well as the foundation or timber structure being raised 150mm above the external ground level, usually 150mm higher than the internal finished floor level.

Raised terrace

Another way of preventing water ingress at this critical junction is to use a raised terrace such as paving slabs on pedestals. Whilst this is the best option if you have a raised terrace area, it is also used when the garden level is lower than your internal ground floor level, such as with a beam and block construction. Further details can be found in the following section.

Level Balcony and Terrace Thresholds

Level Terrace Thresold

When designing a level threshold onto a raised terrace or balcony, even more care needs to be taken to assure that water does not enter the building fabric.

When creating a level threshold over a heated space, care needs to be taken when setting the internal finish floor level and ceiling level to allow for the new insulation. Many people opt for vacuum insulation to this area to allow for a reduced terrace build-up.

Adjustable pedestals can be used to bridge the gap between the level pavers or timber deck with the sloped flat roof. The gaps between the deck material is also key in allowing the water to drain through to the roof and the roof outlet.

Key points to remember

 

  • The threshold including door frame should not be more than 15mm in height overall. Of these 15mm, there should be a minimum number of upstands and slopes, with any upstands higher than 5mm chamfered.
  • The gap between door sill and paving or timber to be a minimum of 10mm.
  • The gap between paving or timber to be a minimum of 6mm.
  • Flat roof to have 1:40 falls for a 1:80 minimum built slope.
  • Ensure all water falls away from the doorway in a single direction.
  • Build a drainage outlet on the opposite side of the flat roof to the threshold.
  • Ensure the flat roof has an overflow.
  • Ensure all waterproofing has a minimum of 75mm upstand under the threshold.
  • Provide a minimum 150mm waterproofing upstand to sides such as brickwork.

Author

Written by Aida Rodriguez-Vega, architect and researcher. At the Detail Library, Aida keeps busy by carrying out technical research and drawing new details for the ever-growing library.

深圳SEO优化公司黄冈网站推广工具报价兴安盟优化价格遵义SEO按效果付费公司山南建网站报价鹤岗SEO按天收费哪家好鹰潭SEO按天扣费价格铜川网站设计模板哪家好肇庆百度seo多少钱曲靖网站建设设计价格阿里网站推广公司本溪seo网站推广多少钱桐城百度网站优化推荐淮北百度网站优化报价龙华网站搜索优化价格双龙seo网站优化公司益阳网站制作忻州阿里店铺运营报价铜川网站改版推荐赣州网站制作设计多少钱三亚seo优化多少钱塔城网站推广工具哪家好赤峰网站建设设计价格汕尾百度网站优化巴中网站建设报价池州外贸网站制作推荐珠海网站制作哪家好唐山外贸网站建设推荐吉祥外贸网站制作报价商丘高端网站设计推荐威海百搜标王推荐歼20紧急升空逼退外机英媒称团队夜以继日筹划王妃复出草木蔓发 春山在望成都发生巨响 当地回应60岁老人炒菠菜未焯水致肾病恶化男子涉嫌走私被判11年却一天牢没坐劳斯莱斯右转逼停直行车网传落水者说“没让你救”系谣言广东通报13岁男孩性侵女童不予立案贵州小伙回应在美国卖三蹦子火了淀粉肠小王子日销售额涨超10倍有个姐真把千机伞做出来了近3万元金手镯仅含足金十克呼北高速交通事故已致14人死亡杨洋拄拐现身医院国产伟哥去年销售近13亿男子给前妻转账 现任妻子起诉要回新基金只募集到26元还是员工自购男孩疑遭霸凌 家长讨说法被踢出群充个话费竟沦为间接洗钱工具新的一天从800个哈欠开始单亲妈妈陷入热恋 14岁儿子报警#春分立蛋大挑战#中国投资客涌入日本东京买房两大学生合买彩票中奖一人不认账新加坡主帅:唯一目标击败中国队月嫂回应掌掴婴儿是在赶虫子19岁小伙救下5人后溺亡 多方发声清明节放假3天调休1天张家界的山上“长”满了韩国人?开封王婆为何火了主播靠辱骂母亲走红被批捕封号代拍被何赛飞拿着魔杖追着打阿根廷将发行1万与2万面值的纸币库克现身上海为江西彩礼“减负”的“试婚人”因自嘲式简历走红的教授更新简介殡仪馆花卉高于市场价3倍还重复用网友称在豆瓣酱里吃出老鼠头315晚会后胖东来又人满为患了网友建议重庆地铁不准乘客携带菜筐特朗普谈“凯特王妃P图照”罗斯否认插足凯特王妃婚姻青海通报栏杆断裂小学生跌落住进ICU恒大被罚41.75亿到底怎么缴湖南一县政协主席疑涉刑案被控制茶百道就改标签日期致歉王树国3次鞠躬告别西交大师生张立群任西安交通大学校长杨倩无缘巴黎奥运